Interconnection intelligence for large-load developers
Amperate reads the public interconnection queue, substation headroom, and equipment lead times, then tells you where your next data center actually fits, what the upgrade costs, and when it can truly energize. Not the date that assumes the transformer shows up on time.
A look inside
A preview of the Site Finder. Substation, utility, and location are redacted on this public page; design partners see the live data.
Developer · Site Finder
| # | Substation | kV · TO | Location | Headroom vs request ▾ | Est. $/kW | Energization | Lead / queue |
|---|---|---|---|---|---|---|---|
| 01 | 230 · |
~180 of 300 MW+120 MW to fit
|
$155/kW | Q2 2031 |
xfmr 144 wk ×1 in queue |
||
| 02 | 230 · |
~110 of 300 MW+190 MW to fit
|
$170/kW | Q3 2031 |
xfmr 128 wk ×1 in queue |
||
| 03 | 230 · |
~95 of 300 MW+205 MW to fit
|
- | - |
existing bay ×1 in queue |
||
| 04 | 230 · |
~60 of 300 MW+240 MW to fit
|
- | - | existing bay |
Illustrative data. Substation, utility, and location redacted for this public preview.
The problem
Interconnection queues carry many times the megawatts the grid can host. Standard timelines quietly assume equipment arrives on schedule, so an energization date can slip by years once a new transformer or GSU is actually ordered. Developers are left guessing which sites have room, what the upgrade will cost, and which queue positions ahead of them are speculative and will drop out.
What Amperate does
Every timeline includes transformer and GSU lead times, so you see the real energization quarter, not the one that assumes equipment on schedule. Model ordering early to recover quarters at a capital risk you can price.
Rank every substation in a market by real headroom against your requested load, with the upgrade gap, estimated interconnection cost per kilowatt, and queue depth inline. The best fit sorts first.
Score queue viability from public signals: financial security posted, site control, developer track record, and megawatts requested against what the substation can host. See the market the way the utility does.
Design partners
Developer-side teams who shape the roadmap and get the full platform. If you are siting large load in PJM or ERCOT and want the honest date before you commit capital, request access to the live demo.